Design-build is a procurement model, not a promise


The four documents that decide the project
A design-build award is decided long before cable is pulled: the owner's program of requirements, the integrator's engineered drawing set, the division-of-work matrix against electrical and low-voltage trades, and the commissioning plan. If any of the four is missing at contract, the gap becomes a change order during installation. My company ran these projects from 1999 to 2020; the failure pattern never changed.
What to demand before award
A schematic per room type, a device schedule with model numbers, an explicit responsibility matrix for conduit, power, network drops and ceiling access, and a commissioning checklist tied to acceptance. Those four are checkable before money moves. A price without them is not a bid; it is an estimate with a signature line.